Probabilistic Time Estimation of Tunneling Projects: The Uri Headrace Tunnel

Author:

Mohammadi MohammadORCID,Spross JohanORCID,Stille Håkan

Abstract

AbstractProbabilistic time estimation is an essential part of proper risk management in tunneling projects. In recent decades, several models have been developed for this purpose, one of which was developed by Isaksson and Stille (Rock Mech Rock Eng 38:373–398, 2005). In this paper, Isaksson and Stille’s probabilistic time and cost estimation model was improved and then applied to estimate the total tunneling time of the headrace tunnel in the Uri hydropower project in India. The improvements allow the user to more accurately account for different types of geological features and disruptive events. The result of the estimation is a distribution of tunneling time. The outcome illustrates how a proper understanding of the geological setting of the project and its effect on construction performance can contribute to effective risk management.

Funder

Svenska Forskningsrådet Formas

Stiftelsen Bergteknisk Forskning

Open access funding provided by Royal Institute of Technology

Publisher

Springer Science and Business Media LLC

Subject

Geology,Geotechnical Engineering and Engineering Geology,Civil and Structural Engineering

Reference45 articles.

1. Benjamin JR, Cornell CA (1970) Probability, statistics, and decision for civil engineers. McGraw-Hill, New York

2. Brantmark J, Stille H (1996) Prediction of squeezing pressure on the Uri Project, Kashmir, India. In Proceedings of ISRM International Symposium-EUROCK. Turin. pp. 1025–1032

3. Cantarelli CC, van Wee B, Molin EJ, Flyvbjerg B (2012a) Different cost performance: different determinants? The case of cost overruns in Dutch transport infrastructure projects. Transp Policy 22:88–95. https://doi.org/10.1016/j.tranpol.2012.04.002

4. Cantarelli CC, Molin EJ, van Wee B, Flyvbjerg B (2012b) Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases. Transp Policy 22:49–56. https://doi.org/10.1016/j.tranpol.2012.04.001

5. Dantata NA, Touran A, Schneck DC (2006) Trends in US rail transit project cost overrun. Transportation Research Board. TRB 2006 Annual Meeting CD-ROM. pp. 1–20.

Cited by 3 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3