Causes, Implications, and Strategies for Project Closeout Delays in Highway Construction

Author:

Tummalapudi Manideep1ORCID,M. Harper Christofer1ORCID,Taylor Timothy R.B.2,Waddle Steve3,Catchings Rachel3ORCID

Affiliation:

1. Department of Construction Management, Colorado State University, Fort Collins, CO

2. Department of Civil Engineering, University of Kentucky, Lexington, KY

3. Kentucky Transportation Center, Lexington, KY

Abstract

In highway construction, completing projects on time is critical. However, when projects are not completed on time, one of the aspects that is often neglected by the state departments of transportation (DOTs), which causes delays in highway construction, is project closeout. The project closeout phase, if delayed, not only has consequences for transportation agencies and contractors, but also leads to substantial social costs to the public. Despite the potential magnitude of the impact, there is limited knowledge about the factors that cause project closeout delays or about strategies for timely highway construction project closeouts. This study identified the causes that delay highway project closeouts, raises awareness of the implications of delays, and provides recommendations for efficient highway project closeout practices. The research methodology included an extensive literature review, a survey questionnaire (40 state DOTs participating), and case studies of eight state DOTs. The results showed that difficulties in attaining the required documentation, claims and litigations, managing multiple funding sources, a lack of urgency from local utilities/entities, and the lack of sufficient DOT project staff are major factors that delay project closeout. When a highway construction project is not closed out in a timely manner, the DOT can be subject to additional costs, obsolete funding sources, loss of project documentation, loss of staff with project knowledge (through retirement/attrition), and potential adverse impacts on internal and external relationships. The authors provide recommendations for state DOTs to mitigate closeout delays and help ensure timely finalization of highway construction projects.

Publisher

SAGE Publications

Subject

Mechanical Engineering,Civil and Structural Engineering

Reference17 articles.

1. Causes of delay in large construction projects

2. Federal Highway Administration. Project Construction and Contract Administration Project Management, Project Closeout. Federal-aid Essentials, 2012. https://www.fhwa.dot.gov/federal-aidessentials/companionresources/02projcloseout.pdf

Cited by 7 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3