A Simulation Approach to the PERT/CPM Time-Cost Trade-Off Problem

Author:

Haga Wayne A.1,Marold Kathryn A.1

Affiliation:

1. Metropolitan State College of Denver, P.O. Box 173362, Campus Box 45, Denver, CO 80217-3362

Abstract

The traditional method of crashing Project Evaluation and Review Technique (PERT) networks ignores the stochastic nature of activity completion times, reducing the stochastic model to a deterministic Critical Path Method (CPM) model and simply using activity time means in calculations. The project is then arbitrarily crashed to some desired completion date, without consideration for what the penalty for late completion of the project is. Additionally, the method ignores the fact that reducing some activity times may reduce the mean project completion time more than others, due to such factors as bottlenecks. The authors use a computer simulation model to determine the order in which activities should be crashed as well as the optimal crashing strategy for a PERT network to minimize the expected value of the total (crash + overrun) cost, given a specified penalty function for late completion of the project. Three extreme network types are examined, each with two different penalty functions.

Publisher

SAGE Publications

Subject

Management of Technology and Innovation,Strategy and Management,Business and International Management

Cited by 9 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3