Analysis of Load Transfer Law of Short Pile-Net Composite Foundation for High-Speed Railway

Author:

Li Shiyou1,Ye Liming1,Jiang Hong1,Chen Zhaofeng2ORCID

Affiliation:

1. Quzhou Traffic Engineering Quality and Safety Supervision Station, Quzhou 324003, China

2. School of Civil Engineering and Architecture, Quzhou University, Quzhou 324000, China

Abstract

Although pile-net composite foundation has been widely used in the construction of high-speed railway, load transfer characteristics of its structural system during the filling of roadbed are seldom studied, so field studies are conducted in the Gan-Long (Ganzhou-Longyan) high-speed railway DK86 + 998.0–DK87 + 191.2 test section, aiming to explore the bearing characteristics of a short pile-net composite foundation over low to medium compressible soil. The study encompasses a field measurement of Earth pressure and pore water pressure which lasted almost two years, and a systematic analysis of variation law of soil pressure between piles and their tops and that of pore pressure in reinforcement zone and retaining layer in medium and low compressibility soil area. The results suggest that the soil in the test section bears the characteristic of a low water content, low porosity ratio, and high liquid limit, with compression factor being approximately 0.25, and test values of the natural soil pressure and the lateral distribution are close to the theoretical values. Soil pressure at the top of the piles is higher than that between the piles by approximately 2.4 times because of the differences in pile-net rigidity. Besides, the soil pressure of the pile-net composite foundation follows the pattern of “jagged” in the transverse direction of the roadbed. The filling load of the composite foundation soil arch is 80 kPa and the composite foundation reaction coefficient is 6.4 kN/m3 when the filling is stable. The pile-soil stress ratio at the shoulder and the center of the line is 3.2 and 2.8, respectively. The change of the hole pressure at the pile end point is larger than that at the reinforcement area, and the side verification short pile can effectively transmit the additional stress of the upper part to the pile end soil layer.

Funder

Science and Technology Project of Zhejiang Provincial Department of Transportation

Publisher

Hindawi Limited

Subject

Mechanical Engineering,Mechanics of Materials,Geotechnical Engineering and Engineering Geology,Condensed Matter Physics,Civil and Structural Engineering

Reference46 articles.

1. Post-construction settlement characteristics analysis and reinforcement effect of soft soil subgrade of high-speed railway;M. Wang;Journal of Civil & Environmental Engineering,2019

2. Difference analysis on the performance of the pile-net composite foundations with different pile types of high-speed railway;M. H. Zhou;Journal of Civil, Architectural & Environmental Engineering,2017

3. Experimental study on CFG pile-(cap-)-net and pile-raft composite foundations of high-speed railway;S. Li;Journal of Railway Science and Engineering,2016

4. Research on reinforce effect of high-speed railway low and medium compressible soil pile-raft (net) foundation;S. Zuo;Journal of Central South University of Science and Technology,2014

5. Experiment study of pile-soil stress ratio of pile-net composite foundation;F. Lian;Bulletin of Science and Technology,2008

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3