The Solan Field Subsea Oil Storage Tank after One Year's Operation West of Shetland, UK - is it a Concept that has Delivered?

Author:

Wheaton S. R.1,Clark S. R.1,Cruickshank P..1

Affiliation:

1. Premier Oil U.K. Limited

Abstract

Abstract The Solan oil field is located offshore in the hostile north Atlantic ~135 kilometres west of the Shetland Isles, UK, in ~135 metre water depth. The field commenced production in 2016. The relatively remote field was developed by four subsea wells tied back to a single slim jacket with a minimum facility topsides. The development includes several innovative features such as full automation, which enables full remote control from an onshore control room in Aberdeen, UK, but strikingly, a world development first involving the installation of an independent steel subsea oil storage tank (SOST) located ~300 metres from the platform. The concept selection, design, fabrication, installation and operation of this novel feature are the subject of this paper. The concept selection of the SOST was driven by several factors including HSE, life cycle cost and operational considerations for this modest sized development in a harsh marine setting. An obvious competitor concept is a subsea well and FPSO alternate; the pros and cons of each approach are compared, using actual field performance now seen versus assumption at the time of concept select. The multiple-compartment SOST is capable of holding almost 300,000 barrels of stabilised oil; it has an in-air weight of ~10,100 tonnes and internal dimensions of 45m x 45m x 25m. The oil is offloaded to a shuttle tanker through a single anchor loading (SAL™) system with the offloading hose stored on the seabed, which is picked up using a pennant line. Oil export to the tanker is driven by hydrostatic displacement by treated seawater from the topsides. This operation is conducted while still producing oil to the SOST. The tank design has novel features for installation, oil-water interface management and corrosion monitoring and subsea inspection. The tank's detailed design and construction phase involved some significant changes as the structural and fatigue life issues were fully analysed and implemented. The installation required significant pre-planning with the use of a very large lifting sling arrangement and a smart air venting and water ballasting system, to then land its eight skirt piles to a tight tolerance on the seabed. Following a commissioning program and trial tanker offload using treated seawater alone, over the past year the SOST has now successfully undergone numerous oil fill and tanker offload operations. There have been learnings regarding the offloading operation but to date the concept has worked in a manner very close to expectation with a full tank offload achieved in less than ~36 hours. The paper closes with a review of how the concept could be improved further considering the experiences now gained from both the project and operational phases.

Publisher

SPE

Cited by 1 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3