Prediction and Scaleup of Waxy Oil Restart Behavior

Author:

Borghi G.-P.1,Correra S.1,Merlini M.2,Carniani C.2

Affiliation:

1. EniTecnologie SpA

2. ENI E&P Div.

Abstract

Abstract A major concern in the design of offshore pipelines is flow restart of waxy oil after a planned or emergency shut-down. As the offshore oil industry encounters increasingly challenging production environments, such as in deepwater or marginal fields, more accurate restart predictions are a requirement for reducing CAPEX and guaranteeing flow assurance. The present state-of-the-art does not generally provide reliable predictions of the pressure required to restart flow in a gelled pipeline; laboratory measurements tend to overestimate the restart pressure, so that empirical factors are used to scale the laboratory data to field conditions. Based on a series of experimental measurements carried out in a upgraded model pipeline, our analysis suggests that compressibility and the appearance of a solid-like fracture at the front of the propagating pressure wave have to be taken into account in order to better model the cold restart process. Introduction As the oil and gas reserves are found in the increasingly challenging production offshore environments, such as in deepwater or marginal fields, flow assurance emerge as one of the key aspects for the economical development of those assets. In case of waxy oils, a major concern is flow restart after a prolonged planned or emergency shutdown. In this situation, the waxy components of the crude oil crystallize and the whole oil undergoes a gelation phase transition. To start-up flow, an extra pressure is required. In order to design the transport facilities from the seafloor to the preliminary processing facility (on spars, TLPs, FPSOs, shore plants) where it is prepared for a subsequent shipment to a refinery, an accurate knowledge of the restart pressure is vital. This allows operators to reduce considerably the capital expenditures avoiding the risk of losing pipelines and delaying production for several months. The present state-of-the-art does not generally provide trustworthy predictions for the pressure required to restart flow in a gelled pipeline. The aim of this work was the development of a new pipeline restart model capable of generating reliable, rather than overly conservative, restart pressure predictions. Experimental For this study, two waxy oils were used. They belong to offshore fields one in West Africa, the other in North Africa. As industry best practice experimental measurements for pressure restart evaluation were carried out with a control stress rheometer and a model pipeline (1). Model Pipeline. A 16 m long, 6 mm internal diameter model pipeline was used. During this study, it was upgraded with a loop and an autoclave in order to be able to saturate the crude oils with gas components at pressure up to 2.0 MPa. The pipeline has four pressure transducers along the pipe and two syringe ISCO pumps control the pressure at the inlet and outlet respectively. The oils were feed to the rig at temperature above the cloud point. They were homogenized and, if necessary, saturated with the desired gas by flowing them in the loop. Then the pipeline test section was cooled at a fixed cooling rate (1.7°C/h). The oil was allowed to age for 66 h before the restart experiment was started1. The setup allowed considering different procedure for the restart, in particular the inlet pump worked in the following modes:At constant flow rate;At constant pressure loading rate ;At constant pressure loading rate in a stepwise sequence2;At constant inlet power (keeping constant the product flow rate times inlet pressure). In Table 1 are reported some of the testing conditions and procedures applied with the model pipeline. Model Pipeline. A 16 m long, 6 mm internal diameter model pipeline was used. During this study, it was upgraded with a loop and an autoclave in order to be able to saturate the crude oils with gas components at pressure up to 2.0 MPa. The pipeline has four pressure transducers along the pipe and two syringe ISCO pumps control the pressure at the inlet and outlet respectively. The oils were feed to the rig at temperature above the cloud point. They were homogenized and, if necessary, saturated with the desired gas by flowing them in the loop. Then the pipeline test section was cooled at a fixed cooling rate (1.7°C/h). The oil was allowed to age for 66 h before the restart experiment was started1. The setup allowed considering different procedure for the restart, in particular the inlet pump worked in the following modes:At constant flow rate;At constant pressure loading rate ;At constant pressure loading rate in a stepwise sequence2;At constant inlet power (keeping constant the product flow rate times inlet pressure). In Table 1 are reported some of the testing conditions and procedures applied with the model pipeline.

Publisher

SPE

Cited by 13 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3