Development of a methodology underlying a deterministic model of construction work arrangements on the basis of the concept of an organizational and technological platform for construction

Author:

Lapidus Azariy A.1ORCID,Motylev Roman V.2ORCID,Sokolnikov Vladimir V.2

Affiliation:

1. Moscow State University of Civil Engineering (National Research University) (MGSU)

2. Saint Petersburg State University of Architecture and Civil Engineering (SPbGASU)

Abstract

Introduction. Presently, intensively developing digital technologies can be contributed to theoretical models, engineering designs, as well as construction implementation methods. The article addresses the justification of a methodology underlying a deterministic model of construction work arrangements, designed to eliminate a methodological gap between theoretical methods of research and simulation, engineering methods of design and methods of implementing solutions to problems of construction processes. Materials and methods. Relations between the key sets of elements of construction processes were identified to justify the methodology, underlying the deterministic model of construction arrangements, using methods of the general theory of systems. Approaches to development of an organizational and technological platform in the construction industry and researches in the field of organizational and technological reliability of construction processes are also provided. Model elements are presented as a consolidated block diagram of methods, technological and administrative procedures, as well as construction process periods. The authors present a system for classifying theoretical models that are applicable to construction process research. Results. The methodology, underlying the deterministic model of construction process arrangements, is justified by a system of linear equations, describing construction process components. Construction process components are determined by the structural block diagram of construction process arrangement methods. Parameters and variables of equations convey a unified organizational and technological construction platform, and they can serve as a constituent of the criterion of meeting scheduled deadlines in the course of evaluating the organizational and technological reliability of the construction process. Conclusions. The methodology, underlying the deterministic model of construction process arrangements, based on the concept of an organizational and technological platform of construction processes, represents a structure of algorithms designed to coordinate decisions concerning construction processes, obtained using various methods. This coordination is implemented using sets of ratios between technological and organizational parameters of construction processes and the criterion of predicted time reserves needed for the implementation of current processes and related engineering operations, given that resources and time are still available according to the construction schedule.

Publisher

Moscow State University of Civil Engineering

Subject

General Medicine

Reference29 articles.

1. Legostaeva O.A. Multifactor models for evaluation of investment projects. Technology and economics of construction. Problems and ways to solve them : collection of scientific papers. Novosibirsk, SGUPS Publishing House, 2004; 139-153. (rus.).

2. Mikhailichenko O.Yu. Organizational reliability of the implementation of construction projects. Proce¬edings of NGASU. Sibstrin. 2011; 14(2):11-15. (rus.).

3. Kuznetsov P.A., Oleinik S.P., Zakharov P.V. Organizational reliability of resource management during the reconstruction of emergency facilities. Housing Construction. 2006; 1:5. (rus.).

4. Kalachev V.L., Kerimov F.Yu., Akopyan A.N. Methodological bases of improvement of organizational and technological processes of qualitative preparation of communications of industrial structures for operation. Defense Complex — Scientific and Technical Progress of Russia. 2006; 2:82-84. (rus.).

5. Abdullaev G.I., Velichkin V.Z., Soldatenko T.N. Improving the organizational and technological reliability of the construction of linear-extended structures by the method of predicting failures. Magazine of Civil Engineering. 2013; 3(38):43-50. DOI: 10.5862/MCE.38.6 (rus.).

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3