SS: Jack-up Technology: Improved Guidelines for the Prediction of Geotechnical Performance of Spudcan Foundations During Installation and Removal of Jack-up Units

Author:

Osborne Julian1,Houlsby G.T.2,Teh K.L.3,Leung C.F.3,Bienen B.4,Cassidy M.J.4,Randolph M.F.4

Affiliation:

1. RPS Energy

2. Oxford University

3. National University of Singapore

4. The University of Western Australia

Abstract

Abstract Incidents of unpredicted, and often adverse, jack-up foundation performance continue to occur regularly, while the safety records of other jack-up activities, such as towing, drilling, structural fatigue, collision, fire and blow-outs have improved significantly. Even with comprehensive site assessment procedures in place, and at a time when the jack-up industry is increasingly focused on the control of risks, foundation incidents continue to occur. To address these issues a Joint Industry Funded Project (" InSafeJIP??) has been launched with the intention of developing a document titled " Improved Guidelines for the Prediction of Geotechnical Performance of Spudcan Foundations during Installation and Removal of Jack-up Units??. This JIP is being supported by a wide range of organizations, with representation from:5 Drilling Contractors 5 Operators 4 Marine Warranty Surveyors1 Classification Authority 1 Legislative Authority 1 JU Designer and Builder2 Geotechnical SI Contractors / ConsultantsThe work is being undertaken by a Project Team drawn from the following Universities:National University of Singapore Oxford University The University of Western Australia This fast track initiative is being project managed by RPS Energy with support from Keppel FELS, and the Guideline is scheduled for Industry release possibly as early as 2010. Introduction The overall safety of offshore operations continues to improve at an appreciable rate, but similar success is not being achieved on the predictability, and consequential safety, of jack-up rigs during installation and extraction operations. Unpredictable jack-up foundation performance during installation regularly leads to rig damage, lost production time and project delay with severe cost implications, and at worst can endanger personnel (Osborne et al., 2006).

Publisher

OTC

Cited by 11 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3