Development of Pile Foundation Bias Factors Using Observed Behavior of Platforms During Hurricane Andrew

Author:

Aggarwal R.K.1,Litton R.W.1,Cornell C.A.2,Tang W.H.3,Chen J.H.4,Murff J.D.5

Affiliation:

1. PMB Engineering

2. CAC Co.

3. Hong Kong University of Science & Technology

4. Chevron Petroleum Technology Company

5. Exxon Production Reasearch Co.

Abstract

Abstract The performance of more than 3,000 offshore platforms in the Gulf of Mexico was observed during the passage of Hurricane Andrew in August 1992. ?IMs event provided an opportunity to test the procedures used for platform analysis and design. A global bias was inform for overall platform capacity and loads in the Andrew Joint Industry Project (JIP) Phase 1.1 It was predicted that the pile foundations of several platform should have failed, but did not. ?lime results indicated that the biases specific to foundation failure modes may be higher than those of jacket failure modes. ?Ile biases in predictions of foundation failure modes were therefore investigated further in this study. ?he work included capacity analysis and calibration of predictions with the observed behave for 3 jacket platforms and 3 caissons using Bayesian updating. Bias factors for two foundation failure mess, lateral shear and overturning, were determined feat structure. Foundation capacity estimates using conventional methods were found to be conservative y biased overall. Introduction Hurricane Andrew was a very intense storm that passed through the Gulf of Mexico in August 1992. While most of the Gulf of Mexico platforms were not adversely affected by Andrew, twenty eight steel jacket platforms were significantly damaged. All of these were installed during 1948 to 1969 and were located in water depths up to 143 feet. In addition, forty seven caissons, nstalled during 1979 to 1991 in water depths up to 113 feet, were also significantly damaged. While foundation failure was identified as the primary cause of damage to most caissons, it was identified as the cause for damage of only one steel jacket platform. An extreme event such as Andrew provides a unique opportunity to study offshore structures tested under fill scale field conditions. By reviewing the platforms that survived, were damaged or failed during the hurricane it is possible to improve our understanding of the behavior of platform during large storm. In October, 1993, Phase I of a joint industry project, "Hurricane Andrew - Effects on Offshore Platforms,''1'3 was completed. This project established that there was bias in the safety factor (capacity to load ratio) by combining the analytical and observed behavior of 13 jacket platforms. The inform bias is characterized as a correction needed to bring analytical results to agreement with the observed results. The capacity analysis performed in Phase I of the Andrew JIP indicated that failure of foundation elements should have occurred in a majority of platforms analyzed, Since this was not observed during post-Andrew inspections, it was concluded that the deterministic analysis was conservatively biased. An overall (system) correction factor, with a mean of 1.2 was established. This correction factor was not specific to any particular failure mode in the jacket structure m its foundation but rather included failures of all types.

Publisher

OTC

Cited by 11 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3