Abstract
PurposeThe energy performance gap (EPG) in building construction has been one of the major barriers to the realization of environmental and economic sustainability in the built environment. Although there have been a few studies addressing this issue, studying this topic with a special focus on the project delivery process has been almost overlooked. Hence, this study aims to address the EPG in building construction through the lens of collaborative and life cycle-based project delivery.Design/methodology/approachIn order to realize the objective of this study, the development of a theoretical framework based on the literature review was followed by a qualitative study in which 21 semi-structured interviews were conducted with Finnish project professionals representing clients, design/planning experts, constructors and building operation/maintenance experts to explore their views on the topic under study.FindingsThe findings reveal the project delivery-related causes of EPG in building construction. Moreover, the obtained results present a collaborative and life cycle-based delivery model that integrates project and product (i.e. building) life cycles, and it is compatible with all types of contractual frameworks in building construction projects.Research limitations/implicationsAlthough the findings of this study significantly contribute to theory and practice in the field of collaborative and sustainable construction project delivery, it is acknowledged that these findings are based on Finnish professionals’ input, and expanding this research to other regions is a potential area for further studies. Moreover, the developed model, although validated in Finland, needs to be tested in a broader context as well to gain wider generalizability.Originality/valueThe obtained results reveal the significance and impact of collaborative and life cycle-based project development and delivery on the realization of environmentally sustainable building construction.