Khosravi Mojtaba,Sarvari Hadi,Chan Daniel W.M.,Cristofaro Matteo,Chen Zhen
Abstract
Purpose
As construction of commercial and recreational complex building projects (CRCBPs) is one of the most important issues in many developing countries and requires a very high cost of implementation, it is important to identify and prioritize the risks of such projects. Therefore, the purpose of this study is to identify and rank the risks of CRCBPs by studying the case of the “Hamedanian Memorial,” a CRCBP in Iran.
Design/methodology/approach
To pursue this aim, a descriptive-survey method was used. The statistical population of the study consists of 30 experienced experts (consultants, contractors and employers) of the “Hamedanian Memorial” project selected according to the Cochran formula and minimum population census. A questionnaire was used as the data collection tool, administered in all stages of risk identification and evaluation, and was devised by using library and field methods based on the literature and research background, as well as interviewing experts in the risk identification and evaluation stages. Kendall’s coefficient of agreement was used to validate the experts’ opinions in the risk identification stage. The ranking in qualitative evaluation was done based on the risk intensity and the cumulative risk index.
Findings
The results show that the risks are associated with exchange rate fluctuation, inflation fluctuation, access to skilled workers, contractors’ claims and foreign threats from international relations.
Originality/value
The results and findings of the present study can be of interest to the executives of large commercial, leisure, public and private projects in developing and developed countries; understanding risks can significantly improve the decision-making process of CRCBPs.
Subject
Management of Technology and Innovation,Strategy and Management,Business and International Management
Reference67 articles.
1. Upper echelons and executive profiles in the construction value chain: evidence from Italy;Project Management Journal,2015
2. Hambrick and Mason’s ‘Upper Echelons Theory’: evolution and open avenues;Journal of Management History,2020
3. Systematic risk management approach for construction projects;Journal of Construction Engineering and Management,1990
4. Identifying and prioritizing the risks of high-power oil and gas projects in Iran using risk breakdown structure and TOPSIS technique;Journal of Economic Research and Policies,2016
Cited by
28 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献