Detecting the most appropriate delay analysis methods for mega airport projects

Author:

Cevikbas Murat,Işık Zeynep

Abstract

PurposeThis study aims to detect the most appropriate delay analysis method in mega airport projects.Design/methodology/approachFirst, the criteria affecting the selection of delay analysis methods were detected through an in-depth literature review and an expert panel, which was conducted with 12 experts who have experience in delay analysis domain in mega airport projects. Later, fuzzy VIKOR (VIsekriterijumska optimizacija i KOmpromisno Resenje) approach was conducted by considering the detected selection criteria and the most common delay analysis methods.FindingsWindows Analysis method was detected as the best option for mega airport projects. It was followed by Time Impact Analysis (TIA), collapsed as-built analysis, as-planned vs as-built method and impacted as-planned method, respectively.Originality/valueEach project has its own characteristics and thus requires specific management techniques; therefore, selecting a delay analysis method without considering the project types and size may cause conflicts between the contracting parties. On the one hand, numerous fruitful studies concerning delay analysis methods have been conducted in the literature, but on the other hand, none of them has considered project characteristics in terms of project size and type while selecting the most appropriate delay analysis method. Moreover, the larger the size of a project is, the more vulnerable it is to encounter with delays. Mega airport construction projects are complex in their nature in that they are large size and involve multi-disciplinary processes; thus, they need special attention in the process of resolving delays. This study intended to fill this gap in the literature by focusing on selection of the most appropriate delay analysis method for mega airport projects, and it is clear that considering the project type and size in the selection of delay analysis methods will provide more reliable outcomes.

Publisher

Emerald

Subject

General Business, Management and Accounting,Building and Construction,Architecture,Civil and Structural Engineering

Reference37 articles.

1. Selection of appropriate schedule delay analysis method: analytical Hierarchy process (AHP),2006

2. Group decision-making based on complex spherical fuzzy VIKOR approach;Knowledge-Based Systems,2021

3. Construction delay analysis techniques;Construction Management and Economics,1996

4. Selecting a delay analysis method in resolving construction claims;International Journal of Project Management,2006

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. Decision Support Framework for the Choice of Delay Analysis Techniques Used in Extension of Time Claims;Journal of Legal Affairs and Dispute Resolution in Engineering and Construction;2024-11

2. A comprehensive review of delay analysis techniques for solving concurrent delays;Engineering, Construction and Architectural Management;2024-02-20

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3