Author:
Moniri Mohammad Reza,Alem Tabriz Akbar,Ayough Ashkan,Zandieh Mostafa
Abstract
Purpose
The purpose of this paper is to propose a new framework for assessing the risks of turnaround projects in upstream oil process plants.
Design/methodology/approach
This study represents a new hybrid framework for turnaround project risk assessment. First, according to experts’ opinions, the project risks were identified using interviews and brainstorming. The most important risks selected by experts and a hybrid multiple-attribute decision-making (MADM) method used to assess and prioritize them. The proposed MADM method uses fuzzy step-wise weight assessment ratio analysis (SWARA) and fuzzy evaluation based on distance from average solution (EDAS) methods based on trapezoidal fuzzy numbers.
Findings
In this research, 28 usual risks of turnaround projects are identified and 10 risks are then selected as the most important ones. The findings show, that among the risks of upstream oil industry turnaround projects from the perspective of experts, the risk of timely financing by the employer, with an appraisal score of 0.83, has the highest rank among the risks and the risk of machine and equipment failure during operation, with an appraisal score of 0.04, has the lowest rank.
Research limitations/implications
The risk analysis based on inputs collected from the experts in the Iranian upstream oil industry, and so the generalization of the results is limited to the context of developing countries, especially oil producer ones. However, the proposed risk analysis methodology and key insights developed can be useful for researchers and practitioners in any other process industry everywhere.
Originality/value
A novel framework for risk assessment is introduced for turnaround projects in the oil industry using MADM methods. There is no literature on using MADM methods for turnaround project risk analysis in the oil and gas industries. Furthermore, this paper presents a hybrid fuzzy method based on SWARA and EDAS.
Reference69 articles.
1. Analysis of pipe-bursting construction risks using probability-impact model;Journal of Engineering, Design and Technology,2018
2. Sales branches performance evaluation: a multiple attribute decision making approach,2014
3. Trends in turnaround maintenance planning: literature review;Journal of Quality in Maintenance Engineering,2019
4. SWARA method,2019
5. Risk-based maintenance – techniques and applications;Journal of Hazardous Materials,2007
Cited by
10 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献