Abstract
Purpose
The purpose of this paper is to enhance the capability in managing the maintenance of the transportation process from a quarry to a crushing plant, measured by the availability value and the process capability value.
Design/methodology/approach
The maintenance management plan consists of plans for three levels of management: strategy, tactical and operational maintenance plans. The Deming cycle is a continuous improvement tool use for controlling and monitoring activities of the plans. There are three Deming cycles according to these plans, the first of which involves the improvement of machine performance and investment evaluation. The second involves the improvement of plans, schedule, and activities of preventive maintenance including autonomous maintenance. The third is for human resource development on maintenance works. Moreover, the feedback of a prior round of each cycle comes early to detect abnormalities that provide better capability in maintenance.
Findings
Three Deming cycles can use for enhancing the maintenance management. The parameters are availability (A) of machines and the capability process (Cpk) of the transportation process. The results of this research state that the availability value of machines increases to 80-92 percent while the process capability value increases to 0.56.
Practical implications
The maintenance management, especially strategic plan, tactical plan and operational plan via the Deming cycle, can be implemented in other medium-sized industries with limited technology and personnel. It was found that the implementation of the plans has continued to progress with the Deming cycle.
Originality/value
This paper proposes how to successfully implement the maintenance management for medium-sized industries with limited technology and personnel. The maintenance management of three levels is carried out simultaneously by using the Deming cycle. This work has proven to be successful which can be expressed in the availability and the capability process values.
Subject
Industrial and Manufacturing Engineering,Strategy and Management,Safety, Risk, Reliability and Quality
Reference14 articles.
1. Preventive maintenance planning using group technology a case study at Arab potash company Jordan;Journal of Quality in Maintenance Engineering,2012
2. Evaluation improvement of production productivity performance using statistical process control, overall equipment efficiency, and autonomous maintenance;Journal of Achievements Procedia Manufacturing,2014
3. OEE enhancement in SMEs through mobile maintenance: a TPM concept;Journal of Quality & Reliability Management,2015
Cited by
5 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献
1. Lean Maintenance Design to Optimize the Manufacturing Process: A Peruvian Textile Company Case;Advances in Science and Technology;2024-04-16
2. Analysis and Improvement of the Maintenance Activity in the Molding Process of a Company in the Cork Industry;Flexible Automation and Intelligent Manufacturing: Establishing Bridges for More Sustainable Manufacturing Systems;2023-08-25
3. Autonomous maintenance preparation system design with axioms;Journal of Quality in Maintenance Engineering;2022-04-22
4. Increased Efficiency in a Garment Sector by the Integration of Lean Manufacturing Tools;2021 IEEE International Conference on Industrial Engineering and Engineering Management (IEEM);2021-12-13
5. Enhancing performance of maintenance in solar power plant;Journal of Quality in Maintenance Engineering;2019-11-14