Abstract
Purpose
In response to the station design and flexible resources allocation of the aircraft moving assembly line, a new problem named flexible resource investment problem based on project splitting (FRIP_PS), which minimizes total cost of resources with a given deadline are proposed in this paper.
Design/methodology/approach
First, a corresponding mathematical model considering project splitting is constructed, which needs to be simultaneously determined together with job scheduling to acquire the optimized project scheduling scheme and resource configurations. Then, an integrated nested optimization algorithm including project splitting policy and job scheduling policy is designed in this paper. In the first stage of the algorithm, a heuristic algorithm designed to get the project splitting scheme and then in the second stage a genetic algorithm with local prospective scheduling strategy is adopted to solve the flexible resource investment problem.
Findings
The heuristic algorithm of project splitting gets better project splitting results through the job shift selection strategy and meanwhile guides the algorithm of the second stage. Furthermore, the genetic algorithm solves resources allocation and job schedule through evaluation rules which can effectively solve the delayed execution of jobs because of improper allocation of flexible resources.
Originality/value
This paper represents a new extension of the resource investment problem based on aircraft moving assembly line. An effective integrated nested optimization algorithm is proposed to specify station splitting scheme, job scheduling scheme and resources allocation in the assembly lines, which is significant for practical engineering applications.
Subject
Industrial and Manufacturing Engineering,Control and Systems Engineering
Reference36 articles.
1. Multi-mode resource availability cost problem with recruitment and release dates for resources;Applied Mathematical Modelling,2014
2. Priority-based heuristics for the multi-skill resource constrained project scheduling problem;Expert Systems with Applications,2016
3. Combining monte-carlo and hyper-heuristic methods for the multi-mode resource-constrained multi-project scheduling problem;Inform Sciences,2016
4. Lower bounds for the multi-skill project scheduling problem with hierarchical levels of skills,2004
5. Multi-objective simulated annealing for the resource-constrained multi-project scheduling problem,2000
Cited by
13 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献